Site

Roof carport framing in progress

East Wing

AA Drywall continuing on wall framing
MEP layout and rough-in on first floor in progress
3rd floor topping slab is complete
2nd floor wall layout in progress

Center Wing

Beams are complete.
AA Drywall laying out walls.
Framing fire walls.
Beginning 3rd floor hollowcore installation.

West Wing

Core drilling in progress
CMU walls are complete
Begin forming and pouring beams